South Shore Country Club Master Plan
Maintenance and Pool Complex Projects 2021-2023


Maintenance Facility Timeline

  • May 2020 - $2.2MM Town Meeting Approval for Site Work/ Construction

  • October 2020 - Pomroy Associates hired as Operating Project Manager

  • December 2020 - RMD Collaborative hired as Project Architects

  • Winter/Spring, 2021 - Permitting Process with local boards

  • May 2021 - Construction Documents/ Cost Estimates Complete

  • July 2021 - Project goes out to Bid for Phase I/Site Work

  • July 2021 - Bid awarded to E Watson

  • September 2021 - Construction Begins

  • April 30, 2022 - $815k for Phase 1 Completion approved at Town Meeting

  • April 2023 - Completed!

Pool Facility Update Timeline

  • April 2017 - CPC/Town Meeting Approve $75k Pool Feasibility Study - Link to study here

  • April 2018 - SSCC Town wide Pool Survey Results

  • 2018 - 2019 - Town reevaluates cost, timing, financing, fundraising

  • September 2019 - Pool closed indefinitely

  • June, 2020 - CPC/Town Meeting Approve $500k Design/Construction Documents

  • September 2021 - Review of Initial Design and Cost Estimates

  • October 2021 - $1MM CPC application submitted

  • April 30, 2022 - 77% Voted “Yes” at Town Meeting to approve $8MM Construction Financing

  • May 14, 2022 - 75% Voted “Yes” on Ballot question to fund new town Pool at SSCC

  • August 2025 - Litigation resolved - Project out to bid for hopeful Summer 2026 completion


Approximately 1500 citizens participated in an April 2018 Town Survey that was included as part of the Feasibility Study. A solid 73% of the respondents indicated that they or members of their household would be concerned it the Town did not have a public pool facility.
— 2018 Town Survey