South Shore Country Club Master Plan
Maintenance and Pool Complex Projects 2021-2023
Maintenance Facility Timeline
May 2020 - $2.2MM Town Meeting Approval for Site Work/ Construction
October 2020 - Pomroy Associates hired as Operating Project Manager
December 2020 - RMD Collaborative hired as Project Architects
Winter/Spring, 2021 - Permitting Process with local boards
May 2021 - Construction Documents/ Cost Estimates Complete
July 2021 - Project goes out to Bid for Phase I/Site Work
July 2021 - Bid awarded to E Watson
September 2021 - Construction Begins
April 30, 2022 - $815k for Phase 1 Completion approved at Town Meeting
April 2023
Expected Completion Date
Pool Facility Update Timeline
April 2017 - CPC/Town Meeting Approve $75k Pool Feasibility Study - Link to study here
April 2018 - SSCC Town wide Pool Survey Results
2018 - 2019 - Town reevaluates cost, timing, financing, fundraising
September 2019 - Pool closed indefinitely
June, 2020 - CPC/Town Meeting Approve $500k Design/Construction Documents
September 2021 - Review of Initial Design and Cost Estimates
October 2021 - $1MM CPC application submitted
April 30, 2022 - 77% Voted “Yes” at Town Meeting to approve $8MM Construction Financing
May 14, 2022 - 75% Voted “Yes” on Ballot question to fund new town Pool at SSCC